Specification for safe operation of oil-immersed transformers

AddTime:2018-12-21 15:20:31   Views:     【 Big Mid Small 】   Print   Close

Baoding oil-immersed transformer is the main distribution equipment, about the use of oil-immersed transformer, the most important problem is safety, so for the relevant staff, master the safe operation rules of baoding oil-immersed transformer, is a necessary condition for work. Below, shandong TVC power equipment co., ltd. will introduce the safe operation procedures of baoding oil-immersed transformer in detail:

1. Before installation of large baoding oil-immersed transformer, safety construction measures must be prepared according to the installation instructions.

2. The nitrogen-filled transformer is not fully nitrogen discharged (the density of oxygen in its gas is >18%), and it is strictly prohibited for staff to enter. No one is allowed to stay in the exhaust hole when filling nitrogen transformer with oil.

3. In the process of oil discharge and oil filtration of large baoding oil-immersed transformer, the shell and side windings must be reliably grounded.

4. When inspecting the lifting core of transformer, do not stack the core on the oil tank, but put it on the clean cushion prepared in advance. Do not do any work on the core until the lifting rope is relaxed.

5. When the transformer lifting cover is inspected, the outer cover shall be removed and placed on clean mat wood before the core inspection is started. A special person shall be set up around the hood for monitoring. It is strictly forbidden to touch the outer cover and any part of the core.

6. Transformer lifting core or lifting cover must rise and fall smoothly.

7. When carrying out internal inspection of transformers, ventilation and lighting must be good, and a special person should be assigned to supervise; Staff should wear work clothes without buttons and pockets, oil-resistant and slip-resistant boots, and the tools brought in must be tied, registered and counted, so as to prevent the tools and sundries left in the body.

8. Flange bolts of outer cover must be tightened symmetrically and evenly.

When inspecting the large transformer core, scaffolding should be set up. Climbing up and down the lead frame is strictly prohibited.

10. The oil storage and oil treatment site must be equipped with sufficient reliable fire fighting equipment, and a clear fire control responsibility system must be formulated. The site shall be flat and clean, and no fire and inflammable and explosive articles shall be allowed within 10 meters.

11. When the transformer accessories are defective and need to be welded, the residual oil shall be released to clean the surface oil and transported to a safe place.

Baoding zhongyi electric material manufacturing co., ltd. is a professional transformer manufacturer in baoding transformer factory, with professional production equipment, lifting, tooling and testing equipment, established a perfect quality management system, product performance indicators have reached the standard.


The company's main products: baoding dry transformer, baoding box transformer, baoding oil-immersed transformer, baoding high and low voltage complete sets of equipment. I companies to follow "detail decides success or failure, honesty molded the future" of the enterprise purpose, adhere to "quality measuring market, seek development by innovation, to management for efficiency" business philosophy, to make my company's products are widely used in power plant, chemical, construction, mining, metallurgy, rail transportation and other industries, to meet the needs of various users, my company rely on superior product quality, thoughtful service, won the trust of our customers.


Prev:The economic significance and maintenance of dry type transformer    Next:What faults will occur in the operation of dry transformers
Back To Top
Copyright ? Baoding Zhongyi Electrical Material Manufacturing Co., Ltd.  All Rights Reserved    Hebei ICP prepared 11024928-2    

冀公網(wǎng)安備 13060802000181號