Baoding general installation and commissioning of oil-immersed transformer than everyone can learn, but some powerful baoding oil-immersed transformer oil-immersed transformer because the use of big power, using time is longer, the installation environment is more complex, so the mass of oil-immersed transformer is different from general of oil-immersed transformer, so we have all been to baoding oil-immersed transformer power to inspect, install and debugging. Our company has rich experience in installation and maintenance of oil-immersed transformer with relatively high power. We have summarized the following:
Oil-immersed transformer
1. Unpacking inspection of high-power baoding oil-immersed transformer before power on:
(1) check whether the voltage regulator box body is damaged in the transportation process;
(2) check the voltage regulator on the brand name and product specifications are consistent;
(3) check the panel of the head, indicator light, button, switch, compensation baoding oil transformer, contact regulator and other devices are intact;
(4) check whether the fastener is loose shift each part of the connection wire is loose or poor contact;
(5) check the pressure regulating system, transmission mechanism of the device is safe and reliable, such as carbon brush dislocation or incomplete fracture, should be replaced in a timely manner.
2. Installation environment of high-power baoding oil-immersed transformer:
(1) compensation type voltage regulator should be installed in the dry ventilation, does not affect the insulation of the voltage regulator in the environment;
(2) there should be a certain space around the voltage regulator, for the future debugging, maintenance, maintenance;
(3) the installation site should be free from serious vibration or turbulence.
3. Wiring before commissioning of high-power baoding oil-immersed transformer:
(1) the voltage regulator input power line section should meet the voltage regulator corresponding capacity of the current value;
(2) the input power line should be connected to the input end of the voltage regulator, and according to the bus color: yellow, green, red respectively connected to A phase, B phase, C phase. Can output the power cord in the output of the voltage regulator, and bus bar color: yellow, green, and red respectively after a phase b phase c phase, neutral zero received by zero "N" column, chassis shell with earth connection, grounding resistance should be less than 0.4 M Ω.
(3) double cabinet or multi-cabinet structure of the voltage regulator, the bus between the cabinets must be connected according to the color, other lines should be connected according to the number.
Baoding zhongyi electric material manufacturing co., ltd. is a professional transformer manufacturer in baoding transformer factory, with professional production equipment, lifting, tooling and testing equipment, established a perfect quality management system, product performance indicators have reached the standard.
The company's main products: baoding dry transformer, baoding box transformer, baoding oil-immersed transformer, baoding high and low voltage complete sets of equipment. I companies to follow "detail decides success or failure, honesty molded the future" of the enterprise purpose, adhere to "quality measuring market, seek development by innovation, to management for efficiency" business philosophy, to make my company's products are widely used in power plant, chemical, construction, mining, metallurgy, rail transportation and other industries, to meet the needs of various users, my company rely on superior product quality, thoughtful service, won the trust of our customers.